COURT DECISIONTender Process Disputes
May the technical specification for catering service procurement provide that workers will be engaged following an interview?
- Case / decision no:
- 2018/210 / 2018/523
- Decision date:
- 12 February 2023
- Court:
- İdare Mahkemesi
- Case number:
- 2018/210
Examining the technical specification provision complained of in the light of the legislation and the explanatory communiqué, the provisions in issue were intended to enable the contracting authority, which is responsible for ensuring that the personnel to be employed on the work meet the requirements of the service and the conditions it has laid down, to discharge that responsibility.