AUTHORITY DECISION4734Tender Process Disputes

Failure to include all work items in the calculation of the estimated cost

Decision number:
2012/UY.III-3555
Decision date:
12 February 2023

Although the tender file sent by the contracting authority did not contain the implementation project for the construction work, it was understood from the successful tenderer's abnormally low tender justification that the project included three lifts.