AUTHORITY DECISION4734Tender Process Disputes
How are periods not specified in the procurement legislation calculated?
- Decision number:
- 2015/UH.I-3172
- Decision date:
- 07 April 2023
Under Article 64 of the Law, where there is no provision on the calculation of written periods, the provisions of the Code of Obligations apply; the question therefore arises whether the period given to tenderers in a request for samples starts on the date of notification or on the working day following notification.