Skip to main content
Kılıç Law Office emblem
AUTHORITY DECISION4734Tender Process Disputes

In continuous service procurement, may a provision be made that acceptance will be carried out monthly as the service is completed?

Decision number:
2021/UH.II-775
Decision date:
07 April 2023

It follows from the General Specification for Service Works that partial acceptance may not be carried out in continuous service works, and that there is no provisional acceptance in such works.