AUTHORITY DECISION4734Tender Process Disputes

In non-personnel-based service procurement, how are contract and general overheads and the threshold value calculated?

Decision number:
2016/UH.I-1892
Decision date:
07 April 2023

Article 79.3.5 of the Public Procurement General Communiqué provides that in abnormally low tender justifications for non-personnel-based service procurement, contract and general overheads are not to be calculated at 4 per cent; contract costs are to be calculated in accordance with the applicable legislation.