AUTHORITY DECISION4734Tender Process Disputes

In tenders for works not spanning more than one year, must the total appropriation for the work be available to the contracting authority?

Decision number:
Decision date:
07 April 2023

The administrative specification and the draft contract contained no payment plan for future years; this is contrary to Article 62 of the Law referred to above, made it impossible to conclude the tender, and required the tender to be cancelled.