AUTHORITY DECISION4734Tender Process Disputes
In tenders for works not spanning more than one year, must the total appropriation for the work be available to the contracting authority?
- Decision number:
- Decision date:
- 07 April 2023
The administrative specification and the draft contract contained no payment plan for future years; this is contrary to Article 62 of the Law referred to above, made it impossible to conclude the tender, and required the tender to be cancelled.