AUTHORITY DECISION4734Tender Process Disputes
May changes that alter the estimated cost be made by addendum?
- Decision number:
- 2012/UY.III-2877
- Decision date:
- 05 April 2023
Given that the addenda issued during the procurement procedure were capable of changing the estimated cost, and that a change of an amount that cannot be determined may be decisive for the outcome of the tender.