AUTHORITY DECISION4734Tender Process Disputes

May the bid validity period be set at 365 days?

Decision number:
2017/UH.I-2242
Decision date:
12 February 2023

In the tender conducted by open procedure, the bid validity period was set at 365 calendar days, while the letters of guarantee submitted as bid bonds were required to have a validity date no earlier than 10 August 2018.