AUTHORITY DECISION4734Tender Process Disputes

Where the commencement and completion dates of the work are fixed, how is the contract price determined if the procurement procedure is prolonged?

Decision number:
2023/UH.I-365
Decision date:
06 April 2023

The draft contract provided that, in works with fixed commencement and completion dates, where the contract cannot be signed and the work begins late because of the evaluation of bids or complaint procedures, the completion date remains fixed and the quantity of work to be carried out may therefore decrease.