How must a progress payment report be prepared and what documents must accompany it?

The progress payment is prepared on the basis of the quantity of work actually carried out during the contract period and the contract prices. The measurement, timesheet, quantity survey, price adjustment and deduction documents must be consistent with the progress payment and capable of review. (See General Specification for Service Works, Article 42; General Specification for Construction Works, Articles 39 and 40.)