If the first tenderer does not sign the contract, may the second be invited?

Where the conditions in the procurement legislation arise, it may be possible to conclude the contract with the tenderer submitting the economically second most advantageous bid. The approval and time limit procedures must be carried out again in accordance with the legislation, having regard to the suitability of the second bid against the estimated cost and to the public interest.