In what cases is an additional performance bond required?

An additional performance bond is required from the contractor where the contract price increases or in the other cases provided for in the legislation. Its amount and timing are calculated according to the contract and the provisions of Law No 4735. Where the contract is terminated, the guarantee and the additional performance bond are also forfeited.