Skip to main content
Kılıç Law Office emblem
FAQ4735Contract Disputes

In what cases is an additional performance bond required?

An additional performance bond is required from the contractor where the contract price increases or in the other cases provided for in the legislation. Its amount and timing are calculated according to the contract and the provisions of Law No 4735. Where the contract is terminated, the guarantee and the additional performance bond are also forfeited.

This question also appears on these pages

Cookie and external content preference

This website does not use advertising, marketing or analytics cookies. Apart from records required for security and to remember your choice, external content such as maps and videos loads only if you allow it. Cookie policy