FAQ4735
In what circumstances may the contracting authority terminate the contract for the contractor's default?
The contractor's breach of contract must constitute one of the grounds for termination in Law No 4735 and in the contract. The warning, the period given, the continuation of the breach and the contractor's fault must each be checked separately against the documents. (See Public Procurement Contracts Law No 4735, Articles 20 to 22 and 25 to 26.)