Is the performance bond always forfeited where the contract is terminated?

Forfeiture of the guarantee depends on the ground for termination. Termination for the contractor's default does not have the same consequence as termination for force majeure or termination attributable to the contracting authority. Where termination is attributable to the contractor, however, the guarantee is forfeited.