May a penalty be applied to the contractor where inspection and acceptance are delayed?
A penalty must be connected with the contractor's own failure to perform its delivery obligation in time. Delay by the contracting authority in the inspection process must not be attributed to the contractor; the delivery and commission dates must be recorded separately. The time spent on inspection and acceptance must not be counted against the delivery period.