When is acceptance carried out in service procurement?
Acceptance is carried out after the service specified in the contract has been completed and the necessary control documents have been prepared. In continuous works, the monthly progress payment check must be distinguished from final acceptance. (See Public Procurement Contracts Law No 4735, Article 11; Regulation on Inspection and Acceptance in Service Procurement, Articles 8 to 14.)