Where the work is increased, how are the price adjustment and progress payment calculated?

An increase in work made in due form becomes part of the contract and the quantities carried out are taken into the progress payment. The price adjustment is calculated separately by reference to the period in which the new quantities were carried out and the price adjustment method in the contract.