Within what limits may the work be increased in a construction contract?

An increase in work arises where, for reasons that could not be foreseen during the contract, an increase in the quantity of the contract work is necessary, the additional work falls within the project underlying the contract, and separating it from the main work is not technically or economically possible without burdening the contracting authority.