Deficiencies Not Preventing Acceptance (Works)
In works, deficiencies not preventing acceptance are deficiencies that do not affect the use, safety or function of the work and whose total value does not exceed 5% of the contract price. In that case provisional acceptance may be carried out; an amount or security is nevertheless retained until the deficiencies are remedied.